Task Dependencies in a SharePoint Gantt Chart: How They Actually Work

6 min readBy Offered as a service by our team

Rolling this out to more teams?

Let our team set up project tracking in SharePoint

We design your project sites, lists, and Power Automate workflows, then train your team so project tracking actually sticks.

Dependencies are what turn a task list into a plan: this cannot start until that finishes. In the free, open-source Smart Gantt Chart web part you create them with one field, and the chart draws the arrows for you.

Link two tasks with Depends On

Click a task in the Gantt or List view to open the task panel, then set Depends On to the predecessor task. Save, and an arrow appears from the predecessor's bar to this task's bar.

Smart Gantt Chart task panel showing the Depends On field used to link a task to its predecessor
Dependencies are set per task with the Depends On field.

How the scheduling links behave

Each arrow represents one of four dependency types. Lead and lag follow the working calendar configured in the web-part settings:

  • Dates shift automatically. Moving a predecessor shifts dependent tasks to keep their links satisfied, and Undo restores the previous schedule.
  • Four link types are available. Finish to Start, Start to Start, Finish to Finish, and Start to Finish can each include positive lag or negative lead in working days.
  • Links stay inside one project. Cross-project dependencies are not supported.
  • Baselines are separate. Set one from the menu to compare current dates with the approved start and finish dates and see finish variance.

Circular and duplicate links are rejected. Links remain inside one project; Portfolio is a rollup of project cards, not a cross-project scheduling engine.

Show the sequence clearly

Two display settings make the chain readable. Turn on dependency arrows so the links render, and turn on the critical path highlight to emphasize the longest chain of linked work. You can also color bars by status, priority, phase or health so a blocked chain stands out.

Smart Gantt Chart timeline with dependency arrows drawn between linked task bars
Dependency arrows drawn between linked tasks on the timeline.

Structure work without dependencies

Not everything needs a link. Two other fields usually do the job better:

  • Phase groups related tasks into a band on the timeline — useful for Discovery, Build, Rollout.
  • Parent Task nests sub-tasks under a summary task so you can collapse detail.
  • Milestone marks a zero-duration checkpoint, drawn as a diamond.

Related guides

Frequently asked questions

Do SharePoint Gantt dependencies move dates automatically?

Yes. Moving a task shifts dependent tasks to keep their links satisfied, using the configured working calendar. A message reports how many tasks moved and provides Undo.

Are there four dependency types like finish-to-start?

Yes. Smart Gantt Chart supports Finish to Start, Start to Start, Finish to Finish, and Start to Finish, with positive lag or negative lead in working days.

Can a task depend on a task in another project?

No. Dependencies work inside one project. The Portfolio view shows project cards side by side but does not link tasks across projects.

The SharePoint project management guides

Build the plan, run it week to week, then share it with the people who only ever see the summary.

Run the project

Was this page helpful?

One click. No form, no email address.

Missing something in SharePoint Smart Gantt Chart? Feature requests and bug reports go straight to the developer on GitHub — no account needed to read, free account to post.

Request a feature

Related tool

SharePoint Smart Gantt Chart

Gantt + Kanban + list view, backed by a SharePoint list. Free, MIT licensed, no sign-up.

Rolling this out to more teams?

Let our team set up project tracking in SharePoint

We design your project sites, lists, and Power Automate workflows, then train your team so project tracking actually sticks.

About the author

Sean Regan

SharePoint & Microsoft 365 consultant with 20+ years of hands-on experience building SPFx web parts, migration tooling and tenant-grade automation. Maintainer of the open-source SharePoint Smart Solutions suite.