Set a Project Baseline in a SharePoint Gantt Chart (and Track Slippage)
A plan without a baseline can only tell you where things stand today. It cannot tell you how far you have moved from what everyone agreed. Smart Gantt Chart lets you save the agreed dates once, then shows the difference on every task for the rest of the project.
When to set it
Set the baseline once the plan is agreed: tasks entered, dates realistic, dependencies linked, and the sponsor has signed off. Setting it earlier just records a draft. If you build plans from an earlier project, see reusing a project plan as a template, then set the baseline after the import.
How to set a baseline
- Open the project in the Gantt view.
- Click the ⋯ menu in the top-right of the toolbar.
- Choose Set Baseline…. The current start and due dates of every task are saved as the baseline.
There is one baseline per project. Running Set Baseline again replaces it, so only re-baseline when the sponsor has formally approved a new plan.
Reading slippage
After the baseline is set, the Gantt draws a baseline bar for each task beside its current bar. Hover a task to see the baseline dates and the finish variance in days. Open a task and go to the Links tab: the Baseline field shows the baseline start and finish and how many working days earlier or later the task now finishes.
Variance uses working days, so set your team's working week and holidays in the web part's property pane first. The same calendar is used for dependency lag and automatic shifting.
Taking it to the status meeting
Use Export Tasks to CSV from the ⋯ menu. The file includes Baseline Start and Baseline Due next to the current dates, so you can sort by the biggest slips. For the meeting itself, see running a weekly status meeting from the Gantt.
Limits to know
- One baseline per project. A new one replaces the old one.
- If your account cannot edit the project list's columns, baselines may be unavailable for that project.
- Each project is separate. There is no baseline across the whole Portfolio.
Get the free Smart Gantt Chart web part to try it on your own plan.
Get your first result in about 10 minutes
Gantt + Kanban + list view, backed by a SharePoint list. Free, MIT licensed, no sign-up.
- Download the .sppkg package from the latest release.
- Upload it to your tenant App Catalog.
- Add the web part to a SharePoint page.
Email me when a new release ships
No marketing spam. One short email when a new release ships. You can unsubscribe anytime.
Frequently asked questions
Can I keep more than one baseline?
No. Each project has one baseline. Choosing Set Baseline again replaces the existing baseline with the current dates.
How is variance measured?
In days between the baseline finish and the current finish. The task panel shows it as working days earlier or later, so weekends and the holidays in your working calendar are skipped.
Why is Set Baseline unavailable for me?
Baseline dates are stored in the project's SharePoint list. If your account cannot edit that list's columns, baselines may be unavailable for that project. Ask a Site Owner to set it.
Are baseline dates included in exports?
Yes. The CSV export includes Baseline Start and Baseline Due columns alongside the task's current dates.
The SharePoint project management guides
Build the plan, run it week to week, then share it with the people who only ever see the summary.
Build the plan
Start a project, add tasks with dates, and get a timeline on a SharePoint page.
Bring a task list, Excel sheet or Microsoft Planner board in through the import wizard.
Group work into phases and mark the dates that people actually care about.
The SharePoint lists the web part creates, who needs which permission, and what that means for governance.
Export a proven plan to Excel, reset the dates, and start every similar project from it.
Two ways to give a long task list structure, and the roll-up behavior to plan around.
Run the project
A 20-minute routine straight from the SharePoint page, ending with a one-click deck.
On Track, At Risk, Overdue or Done, derived from dates and progress instead of typed in.
Assign tasks, filter by assignee, and find the person carrying too much of the plan.
Cut a 400-task timeline down to the slice you need for a single conversation.
Retire completed work without losing the record, and recover a project deleted by mistake.
The Portfolio view: a status card per project with automatic health and a mini timeline.
How simultaneous edits are protected, and the quick edits that save instantly.
Share and compare
What clients and contractors can do in the plan, and the two things an internal owner handles.
Turn the live plan into a steering-committee deck, plus Excel and PNG output.
Where Calendar and Board views stop, and when dependencies and baselines make a Gantt worth it.
Smart Gantt Chart against Microsoft Project, Planner, Smartsheet, Monday and the rest.
The full picture of running projects from SharePoint, in one page.
The free, open-source Gantt web part that runs inside your own tenant.
Was this page helpful?
One click. No form, no email address.
Missing something in SharePoint Smart Gantt Chart? Feature requests and bug reports go straight to the developer on GitHub — no account needed to read, free account to post.
Request a featureRelated tool
SharePoint Smart Gantt Chart
Gantt + Kanban + list view, backed by a SharePoint list. Free, MIT licensed, no sign-up.
Keep reading
SharePoint Gantt Chart with JSON Formatting: What Works, the Limits, and a Free Alternative
JSON formatting can fake a Gantt bar in a SharePoint list. Here is exactly how far it goes, where it breaks, and the free no-code alternative.
Several People Editing One SharePoint Project Plan: How Conflicts Are Handled
A shared plan only works if one person's edit never silently wipes out another's. How Smart Gantt Chart handles simultaneous edits, and the fastest ways to update tasks.
Share a SharePoint Gantt Chart With External Guests and Clients
Run a project plan with a client or contractor inside your own SharePoint site — what Microsoft 365 guests can do in Smart Gantt Chart, and the two workarounds you need.
Rolling this out to more teams?
Let our team set up project tracking in SharePoint
We design your project sites, lists, and Power Automate workflows, then train your team so project tracking actually sticks.
About the author
Sean Regan
SharePoint & Microsoft 365 consultant with 20+ years of hands-on experience building SPFx web parts, migration tooling and tenant-grade automation. Maintainer of the open-source SharePoint Smart Solutions suite.