Set a Project Baseline in a SharePoint Gantt Chart (and Track Slippage)

5 min readBy Offered as a service by our team

A plan without a baseline can only tell you where things stand today. It cannot tell you how far you have moved from what everyone agreed. Smart Gantt Chart lets you save the agreed dates once, then shows the difference on every task for the rest of the project.

When to set it

Set the baseline once the plan is agreed: tasks entered, dates realistic, dependencies linked, and the sponsor has signed off. Setting it earlier just records a draft. If you build plans from an earlier project, see reusing a project plan as a template, then set the baseline after the import.

How to set a baseline

  • Open the project in the Gantt view.
  • Click the ⋯ menu in the top-right of the toolbar.
  • Choose Set Baseline…. The current start and due dates of every task are saved as the baseline.

There is one baseline per project. Running Set Baseline again replaces it, so only re-baseline when the sponsor has formally approved a new plan.

Reading slippage

After the baseline is set, the Gantt draws a baseline bar for each task beside its current bar. Hover a task to see the baseline dates and the finish variance in days. Open a task and go to the Links tab: the Baseline field shows the baseline start and finish and how many working days earlier or later the task now finishes.

Variance uses working days, so set your team's working week and holidays in the web part's property pane first. The same calendar is used for dependency lag and automatic shifting.

Taking it to the status meeting

Use Export Tasks to CSV from the ⋯ menu. The file includes Baseline Start and Baseline Due next to the current dates, so you can sort by the biggest slips. For the meeting itself, see running a weekly status meeting from the Gantt.

Limits to know

  • One baseline per project. A new one replaces the old one.
  • If your account cannot edit the project list's columns, baselines may be unavailable for that project.
  • Each project is separate. There is no baseline across the whole Portfolio.

Get the free Smart Gantt Chart web part to try it on your own plan.

Free · MIT license · no sign-up

Get your first result in about 10 minutes

Gantt + Kanban + list view, backed by a SharePoint list. Free, MIT licensed, no sign-up.

  1. Download the .sppkg package from the latest release.
  2. Upload it to your tenant App Catalog.
  3. Add the web part to a SharePoint page.
Install guide
Download the latest releaseView on GitHub
Email me when a new release ships
Get notified when SharePoint Smart Gantt Chart updates

No marketing spam. One short email when a new release ships. You can unsubscribe anytime.

Frequently asked questions

Can I keep more than one baseline?

No. Each project has one baseline. Choosing Set Baseline again replaces the existing baseline with the current dates.

How is variance measured?

In days between the baseline finish and the current finish. The task panel shows it as working days earlier or later, so weekends and the holidays in your working calendar are skipped.

Why is Set Baseline unavailable for me?

Baseline dates are stored in the project's SharePoint list. If your account cannot edit that list's columns, baselines may be unavailable for that project. Ask a Site Owner to set it.

Are baseline dates included in exports?

Yes. The CSV export includes Baseline Start and Baseline Due columns alongside the task's current dates.

The SharePoint project management guides

Build the plan, run it week to week, then share it with the people who only ever see the summary.

Was this page helpful?

One click. No form, no email address.

Missing something in SharePoint Smart Gantt Chart? Feature requests and bug reports go straight to the developer on GitHub — no account needed to read, free account to post.

Request a feature

Related tool

SharePoint Smart Gantt Chart

Gantt + Kanban + list view, backed by a SharePoint list. Free, MIT licensed, no sign-up.

Rolling this out to more teams?

Let our team set up project tracking in SharePoint

We design your project sites, lists, and Power Automate workflows, then train your team so project tracking actually sticks.

About the author

Sean Regan

SharePoint & Microsoft 365 consultant with 20+ years of hands-on experience building SPFx web parts, migration tooling and tenant-grade automation. Maintainer of the open-source SharePoint Smart Solutions suite.